Plan → House Build

House Build — your GC checklist

Step-by-step to take a kit/shell to a livable, legal house as your own general contractor. Tick each step (your progress saves on this device); the cost column is a planning range for ~2,000 sf, North Texas. (DIY) = you & the wife; amber rows are inspections/sign-offs that gate the next step.

How to use Order of operations

The golden rule of GC'ing: nothing gets covered until it's inspected, and the trades go in a fixed order — under-slab plumbing before the pour, all rough-ins before insulation, insulation before sheetrock. Skip the order and you're cutting open finished walls. It ties to the kit + owner-GC cost ladder on Home and the roadmap.

0 / 0 steps done
Rural-Texas reality check: many unincorporated counties have no city building permit or CO — but your lender, insurer, septic (OSSF), and electric co-op still require inspections. Confirm what your county AHJ enforces; where there's no formal CO, treat Phase 07 as your own safety + loan-draw checklist.

00 Decisions & money

StepPossible cost
$60–170k (kit)
closing fees
$1,000–3,000

01 Design & permits

StepPossible cost
$1,500–4,000
$300–800
$0–1,500
$500–1,500
$0–500
$1,500–4,000

02 Site & utilities

StepPossible cost
$5,000–20,000
$800–2,500
$12–25k (tap $2–10k)
$12,000–18,000
$3,000–10,000

03 Foundation

StepPossible cost
$3,000–6,000
$12,000–30,000

04 Shell & dry-in

StepPossible cost
$15,000–40,000
$8,000–20,000
incl. / $2–4k
$6,000–20,000

05 Interior framing & rough-ins

StepPossible cost
(DIY) $2,000–5,000
$4,000–8,000
$10,000–18,000
$8,000–16,000
(DIY) $500–2,000
$8,000–18,000

06 Interior finish — at your pace

StepPossible cost
(DIY) $4,000–9,000
(DIY) incl.
(DIY) $1,500–4,000
$3,000–10,000
$6,000–20,000
$6,000–20,000
$3,000–8,000
incl.
(DIY) $1,500–4,000
$5,000–15,000

07 Certificate of Occupancy — the legal minimum to move in

Less is more: this is everything that must be in and passing to legally occupy — you finish the rest later (Phase 08). Where there's no formal CO, this is your safety + final-loan-draw list.

RequirementPossible cost

08 Finish over time — after you've moved in

StepPossible cost
(DIY) as you go
(DIY)
$8,000+
$6,000
as you go
Easy-to-miss items (all built into the steps above): engineer's stamp · finished-floor elevation above floodplain · temporary power · builder's-risk insurance · vapor barrier + termite pretreat under the slab · backing/blocking for cabinets & grab bars · bath exhaust fans · attic access · water-heater pan/drain · gutters to the rainwater tanks · 911 address · a draw-schedule inspection at each phase for the loan.

As GC doing the (DIY) work yourself, these ranges land around the $190–230k owner-GC estimate on Home — carry a 10–15% contingency on top. Sub more out and it climbs toward turnkey.